Construction progress

Masonry work, building UM-2.
Masonry work, building UM-2.
17.12.2024
The construction of facade walls from aerated concrete blocks on the 9th floor has begun. The work is progressing at a rapid pace. The next stage is...

The construction of facade walls from aerated concrete blocks on the 9th floor has begun. The work is progressing at a rapid pace.

The next stage is the construction of inter-apartment walls. So we are currently awaiting the delivery of expanded clay blocks

Monolithic works, UM-2 building
Monolithic works, UM-2 building
14.10.2024
Another stage of the UM-2 construction has been completed! Reinforcement and concreting of vertical structures on the 10th floor has been...

Another stage of the UM-2 construction has been completed! Reinforcement and concreting of vertical structures on the 10th floor has been completed

There is still a lot of work ahead, but the pace is not slowing down, and every day brings us closer to the implementation of the project. Accuracy and quality remain our unchanging priorities at every stage of construction

Masonry work, building UM-2.
Masonry work, building UM-2.
24.09.2024
We continue to make intensive progress on our construction site URBAN MARKET-2 The last warm weeks of autumn and good weather contribute to...

We continue to make intensive progress on our construction site URBAN MARKET-2

The last warm weeks of autumn and good weather contribute to comfortable conditions and acceleration of work, so our specialists have already moved to the 8th floor, where they are erecting facade walls from aerated concrete blocks.

Monolithic works, building UM-2/UM-3
Monolithic works, building UM-2/UM-3
03.09.2024
We are pleased to announce that the installation of staircases on the upper floors in the UM-2 and UM-3 buildings has been completed. The...

We are pleased to announce that the installation of staircases on the upper floors in the UM-2 and UM-3 buildings has been completed.

The installation of the stairs ensures safe access to the upper floors, as well as the possibility of moving to the next stages of construction

Stages of construction

Commissioning date II qtr. 2025
Building 2
Completed:
Commissioned
Inhabited
Pre-project work
Development of project documentation
Preparatory work
Basement construction
Construction of the building frame
Construction of external walls
Construction of internal walls
Windows installation
Roof construction
Facades construction
Black box decoration performing
Arrangement of internal engineering networks
Installation of elevator equipment
Publics fine finishing performing
Flats white box decoration performing
Landscaping
more about construction progress

Monolithic works, building UM-2/UM-3

03.09.2024