logo
square E-STORE
$ USD down

Construction progress

Results 2022
Results 2022
26.12.2022
It's time to sum up our work for the year and make plans for the future. Although this year has been very difficult, it has brought us new skills...
It's time to sum up our work for the year and make plans for the future.
Although this year has been very difficult, it has brought us new skills and an understanding that strength lies in unity and support.

3 turn
House #14:
In February and the beginning of March, we completed repairs in the first apartments and started commissioning already in mid-March.
During the year, 90% of the apartments in the house were handed over.

House #15:
Completed communications, rough repairs.
We are finishing the finishing of corridors, stairs and 2 floors have already been completed.
We continue repairs on the next floors.

4 turn
House #4:
We have completed the installation of windows by 60% and continue to work with the roof.
We plan to start working with ventilation.
House #5:
In 2022, the laying of external and internal walls was completed.

House #6:
We completed the monolithic structures of the house and the laying of the outer walls. Now we are laying the interior. Work is already underway on the 3rd floor!

5 turn
House #19:
Since the beginning of the year, we have completed the construction of the pile field, work with the foundation and built two floors of monolithic structures.

House #20:
We completed the construction of the pile field, work with the foundation and built three floors of monolithic structures.

Houses #21-22:
Leader drilling of piles has begun.


Houses above Urban Market
UM-1:
We completed the crushing and testing of piles.

UM-2:
Built 4.5 and 6 floors of monolithic structures.
The laying of the outer and inner walls of the 4th floor was also completed.

UM-3:
We built 5 floors of monolithic structures from 3 to 8.
The laying of the outer walls of the 3rd floor has been completed.

UM-4:
We completed the crushing and testing of piles.

Ход строительства в октябре 2022
Ход строительства в октябре 2022
20.10.2022
Октябрьские новости по строительству уже готовы! Делимся информацией о том,...
Октябрьские новости по строительству уже готовы!

Делимся информацией о том, как строился наш городок за последний месяц:

3 очередь
Дом №14:
Готовим к сдаче 1 этаж.

Дом №15:
11 этаж: устанавливаем кондиционеры. Готовим к сдаче.
10-9 этажа: монтируем плинтуса и натяжные потолки. Завершаем ремонты.
8-7 этажа: укладываем ламинат, монтируем потолок в коридорах.
6-3 этажа: укладываем плитку.
2-1 этажа: разводим сантехнику.

4 очередь
Дом №4:
Завершили монтаж окон на 3-4 этажах и 8-12 этажах.
Готовимся к установке оконных конструкций с 5 по 7 этажа.
Начали обустройство кровли.
Готовимся к устройству вентиляции.

Дом №5:
Выполняем кладку внутренних стен на 11 этаже.
Проводим подготовку к устройству кровли.
Проводим замеры для оконных конструкций.

Дом №6:
Завершили кладку стен на 12 этаже.

5 очередь
Дом №19:
Завершили опалубку перекрытия 1 этажа.
Продолжаем армирование.

Дом №20:
Продолжаем опалубку перекрытия 2 этажа.

Дома №21-22:
Готовимся к работе с полем свай.


Дома над Urban Market
UM-1:
Завершаем испытание свай.

UM-2:
Готовимся к перекрытию шестого этажа.

UM-3:
Выполнили бетонирование вертикальных конструкций 8 этажа.
Готовимся к горизонтальному перекрытию.
Завершили кладку наружных стен на третьем этаже.

UM-4:
Продолжаем давить сваи.

Stages of construction

Commissioning date III qtr. 2025
Building 5
Completed:
Commissioned
Inhabited
Pre-project work
Development of project documentation
Preparatory work
Basement construction
Construction of the building frame
Construction of external walls
Construction of internal walls
Windows installation
Roof construction
Facades construction
Black box decoration performing
Arrangement of internal engineering networks
Installation of elevator equipment
Publics fine finishing performing
Flats white box decoration performing
Landscaping
more about construction progress

Ход строительства в октябре 2022

20.10.2022

House No. 5 is located in the northern part of the residential area. This is a 12-story building — the tallest in the entire town of Avangard. The building is made in a modern, bright style using simple architectural forms. The facade is lined with high-quality waterproof plaster.

Everything has been done in the house for its energy efficiency: it has its own boiler room, insulated walls, a roof insulated and waterproofed with a three-layer material, high-quality metal-plastic windows have been installed, and the front rooms are heated.

The apartments are rented renovated, fully ready for living. Various options and colors of repair materials are available for you to choose from.

Commercial premises are located on the first floor of building No. 5. These are the most profitable objects in ARTVILLE, as they face Spreys street with daily traffic of thousands of people.

ARTVILLE has:

  • Security 24/7
  • Beauty salon
  • Gym and outdoor sports grounds
  • Cafe
  • Shops
  • Kindergarten
  • School
  • Recreation areas
  • Big park
  • Own generator

Here are some additional benefits of the ARTVILLE residential community:

  • High level of energy efficiency
  • Convenient location
  • Developed infrastructure
  • Safety and comfort
  • A community of active and zealous people

If you are looking for the perfect place to live, ARTVILLE residential township is the best choice for you!