Construction progress
Although this year has been very difficult, it has brought us new skills and an understanding that strength lies in unity and support.
3 turn
House #14:
In February and the beginning of March, we completed repairs in the first apartments and started commissioning already in mid-March.
During the year, 90% of the apartments in the house were handed over.
House #15:
Completed communications, rough repairs.
We are finishing the finishing of corridors, stairs and 2 floors have already been completed.
We continue repairs on the next floors.
4 turn
House #4:
We have completed the installation of windows by 60% and continue to work with the roof.
We plan to start working with ventilation.
House #5:
In 2022, the laying of external and internal walls was completed.
House #6:
We completed the monolithic structures of the house and the laying of the outer walls. Now we are laying the interior. Work is already underway on the 3rd floor!
5 turn
House #19:
Since the beginning of the year, we have completed the construction of the pile field, work with the foundation and built two floors of monolithic structures.
House #20:
We completed the construction of the pile field, work with the foundation and built three floors of monolithic structures.
Houses #21-22:
Leader drilling of piles has begun.
Houses above Urban Market
UM-1:
We completed the crushing and testing of piles.
UM-2:
Built 4.5 and 6 floors of monolithic structures.
The laying of the outer and inner walls of the 4th floor was also completed.
UM-3:
We built 5 floors of monolithic structures from 3 to 8.
The laying of the outer walls of the 3rd floor has been completed.
UM-4:
We completed the crushing and testing of piles.
Делимся информацией о том, как строился наш городок за последний месяц:
3 очередь
Дом №14:
Готовим к сдаче 1 этаж.
Дом №15:
11 этаж: устанавливаем кондиционеры. Готовим к сдаче.
10-9 этажа: монтируем плинтуса и натяжные потолки. Завершаем ремонты.
8-7 этажа: укладываем ламинат, монтируем потолок в коридорах.
6-3 этажа: укладываем плитку.
2-1 этажа: разводим сантехнику.
4 очередь
Дом №4:
Завершили монтаж окон на 3-4 этажах и 8-12 этажах.
Готовимся к установке оконных конструкций с 5 по 7 этажа.
Начали обустройство кровли.
Готовимся к устройству вентиляции.
Дом №5:
Выполняем кладку внутренних стен на 11 этаже.
Проводим подготовку к устройству кровли.
Проводим замеры для оконных конструкций.
Дом №6:
Завершили кладку стен на 12 этаже.
5 очередь
Дом №19:
Завершили опалубку перекрытия 1 этажа.
Продолжаем армирование.
Дом №20:
Продолжаем опалубку перекрытия 2 этажа.
Дома №21-22:
Готовимся к работе с полем свай.
Дома над Urban Market
UM-1:
Завершаем испытание свай.
UM-2:
Готовимся к перекрытию шестого этажа.
UM-3:
Выполнили бетонирование вертикальных конструкций 8 этажа.
Готовимся к горизонтальному перекрытию.
Завершили кладку наружных стен на третьем этаже.
UM-4:
Продолжаем давить сваи.
Today Andrei Belkevich, director of the construction company ZEZMAN Holding, will talk about all the recent news on all stages of construction. So what's new?
3 turn
House #14:
Handing over the keys on the fourth floor.
Getting ready to take the third.
We install plumbing and electrical fittings on the first and second floors.
House #15:
12th floor: handing over the keys.
11th floor: preparing for delivery.
10th floor: we are finishing the corridors.
9th floor: laying the laminate.
8th floor: glue wallpaper.
7th floor: laying tiles.
1-6 floors: we continue to putty and dilute plumbing of the fourth stage.
4 turn
House #4:
We completed the laying of windows on the second and third floors.
Getting ready to install on the floors above.
House #5:
We are laying the interior walls on the tenth floor.
House #6:
We are laying the outer walls on the tenth floor.
5 turn
House #19:
We carry out the formwork of the floor of the first floor.
House #20:
We are reinforcing the horizontal ceiling of the second floor.
Houses #21-22:
Getting ready to work with the pile field.
Houses above Urban Market
UM-1:
The piles are 100% crushed. Getting ready for excavation.
UM-2:
We completed the laying of the inner walls on the fourth floor.
UM-3:
Finished pouring concrete on the seventh floor.
Getting ready for the horizontal overlap.
We completed the laying of the outer walls on the third floor.
UM-4:
We continue to crush the piles.
Active work continues on each house: work with a pile field, construction of new floors, installation of windows, repairs and handing over the keys to new apartments to investors. Let's talk about each queue in more detail:
3 turn
14th house
We hand over the keys to the apartments on the 6th floor.
Preparing for delivery 5th floor.
4th floor. install plinth and interior door.
3rd floor: install electrical fittings.
2nd floor: laying laminate flooring and assembling kitchen furniture.
1st floor: getting ready for laying laminate flooring and installing stretch ceilings.
15 house. 12th floor: tiling is 100% complete. We glue the wallpaper, we are preparing to lay the laminate.
11,10,9 floors: we continue to lay the tiles.
Floors 1-8: we continue to putty the apartments and common areas.
We continue facade work.
4 turn
House 4: started installing windows.
5th house: we carry out laying of internal walls on the 9th floor.
6th house: we are laying the outer walls on the 9th floor.
5 turn
Building 19: completed the ceiling of the basement. The horizontal slab of the 1st floor has begun.
Building 20: formwork for the first floor has been completed.
21.22 at home: getting ready to work with the pile field.
Houses above Urban Market
UM-1: fields are suppressed by 100%. Getting ready for excavation.
UM-2: we continue laying the outer walls on the 4th floor.
UM-3: we continue to reinforce the horizontal ceiling of the 7th floor.
UM-4: we continue to crush the piles.
Follow the news! We will continue to share construction reports.
Stages of construction
Construction progress in July 2022
01.08.2022ARTVILLE is an ensemble of 26 buildings, as well as a multifunctional living mall, located in cozy Avangard. Each house is characterized by a modern style with an emphasis on simple architectural forms and bright colors.
In order to achieve high energy efficiency, building #22 is equipped with its own boiler room, insulated walls and a waterproof insulated three-layer roof. The windows are made of high-quality metal-plastic, and the front ones are heated, providing comfort and keeping warm.
Apartments in the new building No. 22 are offered for purchase with ready repairs - this is not the case in every residential complex in Odessa. You can choose from various options and color palettes for repair materials, as well as consider the possibility of additional equipment with furniture and household appliances.
The first floor of building No. 22 is intended for commercial premises that benefit from access to the Artville Park. Here you have the opportunity to establish your own profitable business or invest in premises for further rental.