logo
square E-STORE
$ USD down

Construction progress

Results 2022
Results 2022
26.12.2022
It's time to sum up our work for the year and make plans for the future. Although this year has been very difficult, it has brought us new skills...
It's time to sum up our work for the year and make plans for the future.
Although this year has been very difficult, it has brought us new skills and an understanding that strength lies in unity and support.

3 turn
House #14:
In February and the beginning of March, we completed repairs in the first apartments and started commissioning already in mid-March.
During the year, 90% of the apartments in the house were handed over.

House #15:
Completed communications, rough repairs.
We are finishing the finishing of corridors, stairs and 2 floors have already been completed.
We continue repairs on the next floors.

4 turn
House #4:
We have completed the installation of windows by 60% and continue to work with the roof.
We plan to start working with ventilation.
House #5:
In 2022, the laying of external and internal walls was completed.

House #6:
We completed the monolithic structures of the house and the laying of the outer walls. Now we are laying the interior. Work is already underway on the 3rd floor!

5 turn
House #19:
Since the beginning of the year, we have completed the construction of the pile field, work with the foundation and built two floors of monolithic structures.

House #20:
We completed the construction of the pile field, work with the foundation and built three floors of monolithic structures.

Houses #21-22:
Leader drilling of piles has begun.


Houses above Urban Market
UM-1:
We completed the crushing and testing of piles.

UM-2:
Built 4.5 and 6 floors of monolithic structures.
The laying of the outer and inner walls of the 4th floor was also completed.

UM-3:
We built 5 floors of monolithic structures from 3 to 8.
The laying of the outer walls of the 3rd floor has been completed.

UM-4:
We completed the crushing and testing of piles.

Ход строительства в октябре 2022
Ход строительства в октябре 2022
20.10.2022
Октябрьские новости по строительству уже готовы! Делимся информацией о том,...
Октябрьские новости по строительству уже готовы!

Делимся информацией о том, как строился наш городок за последний месяц:

3 очередь
Дом №14:
Готовим к сдаче 1 этаж.

Дом №15:
11 этаж: устанавливаем кондиционеры. Готовим к сдаче.
10-9 этажа: монтируем плинтуса и натяжные потолки. Завершаем ремонты.
8-7 этажа: укладываем ламинат, монтируем потолок в коридорах.
6-3 этажа: укладываем плитку.
2-1 этажа: разводим сантехнику.

4 очередь
Дом №4:
Завершили монтаж окон на 3-4 этажах и 8-12 этажах.
Готовимся к установке оконных конструкций с 5 по 7 этажа.
Начали обустройство кровли.
Готовимся к устройству вентиляции.

Дом №5:
Выполняем кладку внутренних стен на 11 этаже.
Проводим подготовку к устройству кровли.
Проводим замеры для оконных конструкций.

Дом №6:
Завершили кладку стен на 12 этаже.

5 очередь
Дом №19:
Завершили опалубку перекрытия 1 этажа.
Продолжаем армирование.

Дом №20:
Продолжаем опалубку перекрытия 2 этажа.

Дома №21-22:
Готовимся к работе с полем свай.


Дома над Urban Market
UM-1:
Завершаем испытание свай.

UM-2:
Готовимся к перекрытию шестого этажа.

UM-3:
Выполнили бетонирование вертикальных конструкций 8 этажа.
Готовимся к горизонтальному перекрытию.
Завершили кладку наружных стен на третьем этаже.

UM-4:
Продолжаем давить сваи.

Construction progress in August 2022
Construction progress in August 2022
06.09.2022
August news from the construction site of ARTVILLE and Urban Market. Today Andrei Belkevich, director of the construction company ZEZMAN...
August news from the construction site of ARTVILLE and Urban Market.


Today Andrei Belkevich, director of the construction company ZEZMAN Holding, will talk about all the recent news on all stages of construction. So what's new?



3 turn
House #14:
Handing over the keys on the fourth floor.
Getting ready to take the third.
We install plumbing and electrical fittings on the first and second floors.

House #15:
12th floor: handing over the keys.
11th floor: preparing for delivery.
10th floor: we are finishing the corridors.
9th floor: laying the laminate.
8th floor: glue wallpaper.
7th floor: laying tiles.
1-6 floors: we continue to putty and dilute plumbing of the fourth stage.

4 turn
House #4:
We completed the laying of windows on the second and third floors.
Getting ready to install on the floors above.

House #5:
We are laying the interior walls on the tenth floor.

House #6:
We are laying the outer walls on the tenth floor.

5 turn
House #19:
We carry out the formwork of the floor of the first floor.

House #20:
We are reinforcing the horizontal ceiling of the second floor.


Houses #21-22:
Getting ready to work with the pile field.


Houses above Urban Market
UM-1:

The piles are 100% crushed. Getting ready for excavation.
UM-2:

We completed the laying of the inner walls on the fourth floor.
UM-3:

Finished pouring concrete on the seventh floor.
Getting ready for the horizontal overlap.
We completed the laying of the outer walls on the third floor.

UM-4:
We continue to crush the piles.


Construction progress in July 2022
Construction progress in July 2022
01.08.2022
We have collected for you all the good news on the construction of a residential town ARTVILLE and Urban Market! Active work continues on each...
We have collected for you all the good news on the construction of a residential town ARTVILLE and Urban Market!

Active work continues on each house: work with a pile field, construction of new floors, installation of windows, repairs and handing over the keys to new apartments to investors. Let's talk about each queue in more detail:

3 turn
14th house
We hand over the keys to the apartments on the 6th floor.
Preparing for delivery 5th floor.
4th floor. install plinth and interior door.
3rd floor: install electrical fittings.
2nd floor: laying laminate flooring and assembling kitchen furniture.
1st floor: getting ready for laying laminate flooring and installing stretch ceilings.

15 house. 12th floor: tiling is 100% complete. We glue the wallpaper, we are preparing to lay the laminate.
11,10,9 floors: we continue to lay the tiles.
Floors 1-8: we continue to putty the apartments and common areas.
We continue facade work.


4 turn
House 4: started installing windows.
5th house: we carry out laying of internal walls on the 9th floor.
6th house: we are laying the outer walls on the 9th floor.


5 turn
Building 19: completed the ceiling of the basement. The horizontal slab of the 1st floor has begun.
Building 20: formwork for the first floor has been completed.
21.22 at home: getting ready to work with the pile field.



Houses above Urban Market
UM-1: fields are suppressed by 100%. Getting ready for excavation.
UM-2: we continue laying the outer walls on the 4th floor.
UM-3: we continue to reinforce the horizontal ceiling of the 7th floor.
UM-4: we continue to crush the piles.


Follow the news! We will continue to share construction reports.

Stages of construction

Commissioning date II qtr. 2026
Building 21
Completed:
Commissioned
Inhabited
Pre-project work
Development of project documentation
Preparatory work
Basement construction
Construction of the building frame
Construction of external walls
Construction of internal walls
Windows installation
Roof construction
Facades construction
Black box decoration performing
Arrangement of internal engineering networks
Installation of elevator equipment
Publics fine finishing performing
Flats white box decoration performing
Landscaping
more about construction progress

Construction progress in July 2022

01.08.2022

Aesthetics, convenience and functionality are all about house #21 of the residential town of ARTVILLE. Inside the building, in addition to the apartment, you have a convenient elevator, including a freight one, free wheelchairs on the -1st floor. Additionally, you can purchase a storage room on the basement floor or on one of the floors of the building.

Apartments here are rented with ready repairs. So after moving, you don't have to wait for the neighbors to finish their repairs.

House 21 is L-shaped. Therefore, here you can find an apartment with windows to any side of the world. Adjacent to it is the Artville Park, which culminates in the multifunctional Urban Market. This is the basis of the town's infrastructure. There is a school, a kindergarten, the necessary household and entertainment infrastructure. The green park is filled with children's and sports grounds, recreation areas, shops, cafes and essential services.

The internal infrastructure of the house is well thought out for your safety and comfort. Each floor has a security system that includes 24-hour video surveillance, smoke and fire detectors. On the -1st floor you have a free wheelchair accessible only for residents of the building. Here you can leave your bicycles and baby carriages so as not to clutter up the apartment.

Buy an apartment in the best new building No. 21 ARTVILLE — live comfortably and safely in Odessa!