Construction progress
Although this year has been very difficult, it has brought us new skills and an understanding that strength lies in unity and support.
3 turn
House #14:
In February and the beginning of March, we completed repairs in the first apartments and started commissioning already in mid-March.
During the year, 90% of the apartments in the house were handed over.
House #15:
Completed communications, rough repairs.
We are finishing the finishing of corridors, stairs and 2 floors have already been completed.
We continue repairs on the next floors.
4 turn
House #4:
We have completed the installation of windows by 60% and continue to work with the roof.
We plan to start working with ventilation.
House #5:
In 2022, the laying of external and internal walls was completed.
House #6:
We completed the monolithic structures of the house and the laying of the outer walls. Now we are laying the interior. Work is already underway on the 3rd floor!
5 turn
House #19:
Since the beginning of the year, we have completed the construction of the pile field, work with the foundation and built two floors of monolithic structures.
House #20:
We completed the construction of the pile field, work with the foundation and built three floors of monolithic structures.
Houses #21-22:
Leader drilling of piles has begun.
Houses above Urban Market
UM-1:
We completed the crushing and testing of piles.
UM-2:
Built 4.5 and 6 floors of monolithic structures.
The laying of the outer and inner walls of the 4th floor was also completed.
UM-3:
We built 5 floors of monolithic structures from 3 to 8.
The laying of the outer walls of the 3rd floor has been completed.
UM-4:
We completed the crushing and testing of piles.
Делимся информацией о том, как строился наш городок за последний месяц:
3 очередь
Дом №14:
Готовим к сдаче 1 этаж.
Дом №15:
11 этаж: устанавливаем кондиционеры. Готовим к сдаче.
10-9 этажа: монтируем плинтуса и натяжные потолки. Завершаем ремонты.
8-7 этажа: укладываем ламинат, монтируем потолок в коридорах.
6-3 этажа: укладываем плитку.
2-1 этажа: разводим сантехнику.
4 очередь
Дом №4:
Завершили монтаж окон на 3-4 этажах и 8-12 этажах.
Готовимся к установке оконных конструкций с 5 по 7 этажа.
Начали обустройство кровли.
Готовимся к устройству вентиляции.
Дом №5:
Выполняем кладку внутренних стен на 11 этаже.
Проводим подготовку к устройству кровли.
Проводим замеры для оконных конструкций.
Дом №6:
Завершили кладку стен на 12 этаже.
5 очередь
Дом №19:
Завершили опалубку перекрытия 1 этажа.
Продолжаем армирование.
Дом №20:
Продолжаем опалубку перекрытия 2 этажа.
Дома №21-22:
Готовимся к работе с полем свай.
Дома над Urban Market
UM-1:
Завершаем испытание свай.
UM-2:
Готовимся к перекрытию шестого этажа.
UM-3:
Выполнили бетонирование вертикальных конструкций 8 этажа.
Готовимся к горизонтальному перекрытию.
Завершили кладку наружных стен на третьем этаже.
UM-4:
Продолжаем давить сваи.
Today Andrei Belkevich, director of the construction company ZEZMAN Holding, will talk about all the recent news on all stages of construction. So what's new?
3 turn
House #14:
Handing over the keys on the fourth floor.
Getting ready to take the third.
We install plumbing and electrical fittings on the first and second floors.
House #15:
12th floor: handing over the keys.
11th floor: preparing for delivery.
10th floor: we are finishing the corridors.
9th floor: laying the laminate.
8th floor: glue wallpaper.
7th floor: laying tiles.
1-6 floors: we continue to putty and dilute plumbing of the fourth stage.
4 turn
House #4:
We completed the laying of windows on the second and third floors.
Getting ready to install on the floors above.
House #5:
We are laying the interior walls on the tenth floor.
House #6:
We are laying the outer walls on the tenth floor.
5 turn
House #19:
We carry out the formwork of the floor of the first floor.
House #20:
We are reinforcing the horizontal ceiling of the second floor.
Houses #21-22:
Getting ready to work with the pile field.
Houses above Urban Market
UM-1:
The piles are 100% crushed. Getting ready for excavation.
UM-2:
We completed the laying of the inner walls on the fourth floor.
UM-3:
Finished pouring concrete on the seventh floor.
Getting ready for the horizontal overlap.
We completed the laying of the outer walls on the third floor.
UM-4:
We continue to crush the piles.
Active work continues on each house: work with a pile field, construction of new floors, installation of windows, repairs and handing over the keys to new apartments to investors. Let's talk about each queue in more detail:
3 turn
14th house
We hand over the keys to the apartments on the 6th floor.
Preparing for delivery 5th floor.
4th floor. install plinth and interior door.
3rd floor: install electrical fittings.
2nd floor: laying laminate flooring and assembling kitchen furniture.
1st floor: getting ready for laying laminate flooring and installing stretch ceilings.
15 house. 12th floor: tiling is 100% complete. We glue the wallpaper, we are preparing to lay the laminate.
11,10,9 floors: we continue to lay the tiles.
Floors 1-8: we continue to putty the apartments and common areas.
We continue facade work.
4 turn
House 4: started installing windows.
5th house: we carry out laying of internal walls on the 9th floor.
6th house: we are laying the outer walls on the 9th floor.
5 turn
Building 19: completed the ceiling of the basement. The horizontal slab of the 1st floor has begun.
Building 20: formwork for the first floor has been completed.
21.22 at home: getting ready to work with the pile field.
Houses above Urban Market
UM-1: fields are suppressed by 100%. Getting ready for excavation.
UM-2: we continue laying the outer walls on the 4th floor.
UM-3: we continue to reinforce the horizontal ceiling of the 7th floor.
UM-4: we continue to crush the piles.
Follow the news! We will continue to share construction reports.
Stages of construction
Construction progress in July 2022
01.08.2022House No. 20 is a modern and comfortable residential complex located in the village of Avangard. It consists of 12 floors and has an L-shape, thanks to which the apartments can be admired on any side of the world.
Inside the house there is everything for a comfortable life:
- Convenient elevators, including freight elevators, for moving around the house.
- Free wheelchair storage on the -1st floor for storing bicycles and baby carriages.
- Storerooms on the basement floor or on one of the floors of the building.
- Apartments with ready repairs, so that you can move in immediately.
- Security system on each floor with 24-hour video surveillance, smoke and fire detectors.
The house is located in the center of the ARTVILLE residential town, where there is all the necessary infrastructure:
- School
- Kindergarten
- Shopping centers
- Shops
- Restaurants
- Cafe
- Green park
Buy an apartment in the best new building No. 20 ARTVILLE — live comfortably and safely in Odessa!