Construction progress
Construction progress in September 2021
09.09.2021
In September, construction of the fifth phase began in the residential town of ARTVILLE. These are houses No. 19 and 20 - we are preparing a pile...
In September, construction of the fifth phase began in the residential town of ARTVILLE. These are houses No. 19 and 20 - we are preparing a pile field for them, we are leading the piles.
In the houses of the third stage, we insulate and glaze the facades, carry out internal work and do the wiring of communications. A little more and it will be possible to start finishing work.
In the fourth stage of construction, we continue monolithic work and laying walls. We build Urban Market houses.
In the houses of the third stage, we insulate and glaze the facades, carry out internal work and do the wiring of communications. A little more and it will be possible to start finishing work.
In the fourth stage of construction, we continue monolithic work and laying walls. We build Urban Market houses.
Permits
Лицензия на создание объектов архитектуры
Permission to perform construction works dated 11/14/2017
Permission to perform construction works dated 25.01.2019
Разрешение на выполнение строительных работ от 12.08.2021
Stages of construction
Commissioning date IV qtr. 2026
Building 16
Commissioned
Inhabited
Pre-project work
Development of project documentation
Preparatory work
Basement construction
Construction of the building frame
Construction of external walls
Construction of internal walls
Windows installation
Roof construction
Facades construction
Black box decoration performing
Arrangement of internal engineering networks
Installation of elevator equipment
Publics fine finishing performing
Flats white box decoration performing
Landscaping
more about construction progress