Construction progress
Although this year has been very difficult, it has brought us new skills and an understanding that strength lies in unity and support.
3 turn
House #14:
In February and the beginning of March, we completed repairs in the first apartments and started commissioning already in mid-March.
During the year, 90% of the apartments in the house were handed over.
House #15:
Completed communications, rough repairs.
We are finishing the finishing of corridors, stairs and 2 floors have already been completed.
We continue repairs on the next floors.
4 turn
House #4:
We have completed the installation of windows by 60% and continue to work with the roof.
We plan to start working with ventilation.
House #5:
In 2022, the laying of external and internal walls was completed.
House #6:
We completed the monolithic structures of the house and the laying of the outer walls. Now we are laying the interior. Work is already underway on the 3rd floor!
5 turn
House #19:
Since the beginning of the year, we have completed the construction of the pile field, work with the foundation and built two floors of monolithic structures.
House #20:
We completed the construction of the pile field, work with the foundation and built three floors of monolithic structures.
Houses #21-22:
Leader drilling of piles has begun.
Houses above Urban Market
UM-1:
We completed the crushing and testing of piles.
UM-2:
Built 4.5 and 6 floors of monolithic structures.
The laying of the outer and inner walls of the 4th floor was also completed.
UM-3:
We built 5 floors of monolithic structures from 3 to 8.
The laying of the outer walls of the 3rd floor has been completed.
UM-4:
We completed the crushing and testing of piles.
Делимся информацией о том, как строился наш городок за последний месяц:
3 очередь
Дом №14:
Готовим к сдаче 1 этаж.
Дом №15:
11 этаж: устанавливаем кондиционеры. Готовим к сдаче.
10-9 этажа: монтируем плинтуса и натяжные потолки. Завершаем ремонты.
8-7 этажа: укладываем ламинат, монтируем потолок в коридорах.
6-3 этажа: укладываем плитку.
2-1 этажа: разводим сантехнику.
4 очередь
Дом №4:
Завершили монтаж окон на 3-4 этажах и 8-12 этажах.
Готовимся к установке оконных конструкций с 5 по 7 этажа.
Начали обустройство кровли.
Готовимся к устройству вентиляции.
Дом №5:
Выполняем кладку внутренних стен на 11 этаже.
Проводим подготовку к устройству кровли.
Проводим замеры для оконных конструкций.
Дом №6:
Завершили кладку стен на 12 этаже.
5 очередь
Дом №19:
Завершили опалубку перекрытия 1 этажа.
Продолжаем армирование.
Дом №20:
Продолжаем опалубку перекрытия 2 этажа.
Дома №21-22:
Готовимся к работе с полем свай.
Дома над Urban Market
UM-1:
Завершаем испытание свай.
UM-2:
Готовимся к перекрытию шестого этажа.
UM-3:
Выполнили бетонирование вертикальных конструкций 8 этажа.
Готовимся к горизонтальному перекрытию.
Завершили кладку наружных стен на третьем этаже.
UM-4:
Продолжаем давить сваи.
Today Andrei Belkevich, director of the construction company ZEZMAN Holding, will talk about all the recent news on all stages of construction. So what's new?
3 turn
House #14:
Handing over the keys on the fourth floor.
Getting ready to take the third.
We install plumbing and electrical fittings on the first and second floors.
House #15:
12th floor: handing over the keys.
11th floor: preparing for delivery.
10th floor: we are finishing the corridors.
9th floor: laying the laminate.
8th floor: glue wallpaper.
7th floor: laying tiles.
1-6 floors: we continue to putty and dilute plumbing of the fourth stage.
4 turn
House #4:
We completed the laying of windows on the second and third floors.
Getting ready to install on the floors above.
House #5:
We are laying the interior walls on the tenth floor.
House #6:
We are laying the outer walls on the tenth floor.
5 turn
House #19:
We carry out the formwork of the floor of the first floor.
House #20:
We are reinforcing the horizontal ceiling of the second floor.
Houses #21-22:
Getting ready to work with the pile field.
Houses above Urban Market
UM-1:
The piles are 100% crushed. Getting ready for excavation.
UM-2:
We completed the laying of the inner walls on the fourth floor.
UM-3:
Finished pouring concrete on the seventh floor.
Getting ready for the horizontal overlap.
We completed the laying of the outer walls on the third floor.
UM-4:
We continue to crush the piles.
ZEZMAN Holding continues to build cities by supporting the President's "Economic Patriotism" initiative. We fulfill our obligations to partners and investors, support the Armed Forces of Ukraine and help maintain the stability of the economy.
Permits
Stages of construction
Handing over the keys to house number 15
06.09.2022House #14 of the ARTVILLE residential town is a bright accent that enlivens the environment. The new building is located in Odesa, opposite 7km, and is made in a modern architectural style using bright colors. The facade is lined with high-quality durable plaster, which not only decorates the house, but also protects it from external influences.
Apartments in building No. 4 are rented out with modern renovations using quality materials. They are spacious, comfortable and have a modern design. The building has an individual heating system that allows residents to adjust the temperature in the apartment at their discretion. In addition, the repair includes the installation of air conditioners, some furniture and appliances.
House No. 4 is not just a place to live, but also an investment in the future. It is located in a convenient location, close to developed infrastructure. Everything you need for a comfortable life is here:
- 24/7 security with patrols and video surveillance
- Beauty salon
- Gym
- Cafe
- Shops
- Kindergarten and school
- Recreation areas
- Big park
- Communities of interest
ARTVILLE residential town is an ideal place for those who want to buy an apartment in a modern, comfortable new building in Odessa. Here you will find everything you need for a happy life: cozy apartments, developed infrastructure, security and a comfortable living environment.